The Walk From Travis Heights to the Lake Changed This Year. The Lake Crossing Comes Back Before Woodland Does.

If you head north from Big Stacy toward Lady Bird Lake this week, how many of your old routes still work?

Most of them still work. The ones that don't are all near I-35, and they closed for different reasons with very different timelines. Two closures belong to the same piece of work, a new pedestrian bridge over the lake on the east side of the highway, and that work is scheduled to finish in months. The third is Woodland Avenue, and its replacement is a separate bridge in a later phase. KUT reported that construction on it could start as soon as 2029. Knowing which wait is which explains why the rest of this winter looks the way it does.

The Routes That Work in November

The Trail Conservancy keeps a running detour list for the Butler Hike-and-Bike Trail, last updated October 26. Here is how it lines up with TxDOT's Lady Bird Lake segment page.

Route from Travis Heights

Status for the rest of 2026

Source

South-shore boardwalk at I-35

Open after the full closure of Oct. 12–18; access is limited along a portion through early 2027

The Trail Conservancy

Trail under the I-35 bridge

Open to trail users

The Trail Conservancy

Crossing the lake on the west side of I-35

West-side sidewalk open

The Trail Conservancy

Crossing the lake on the east side of I-35

Closed since the week of Feb. 9, 2026, for about a year

The Trail Conservancy

Pedestrian ramp to the boardwalk along the northbound frontage road at Riverside

Closed from Feb. 16, 2026, through 2029

The Trail Conservancy

Woodland Avenue under I-35

Permanently closed to through traffic

TxDOT

From the neighborhood, the boardwalk's access points sit at South Lakeshore Boulevard east of I-35 and at the trail entrance west of I-35. To reach the north shore, the Trail Conservancy points people to the South Congress bridge or the new Wishbone Pedestrian Bridge at Pleasant Valley. You can also use the west-side I-35 sidewalk, which is still open.

For a full loop from the east end of Travis Heights, that means crossing at South Congress or on the west side of I-35. Going the long way east to Pleasant Valley turns the walk into the full loop that the Wishbone Bridge made possible this year. We covered that loop from the Barton Hills end in our ACL detour guide.

Why the Boardwalk Is Narrowed

The boardwalk restrictions and the closed east-side crossing are not separate inconveniences. According to the Trail Conservancy, the October closure was there "to accommodate construction of the pedestrian bridge." The reduced access that followed covers "ongoing construction of the pedestrian bridge east of I-35."

TxDOT's construction plan puts that bridge in the first of four phases. The Lady Bird Lake segment construction document lays out the order:

  1. Phase I: widen I-35 shoulders, build the Lady Bird Lake east pedestrian bridge, build the northbound frontage road, rebuild the Riverside Drive intersection, and add a shared-use path from Woodward Street to SH 71/Ben White Boulevard.
  2. Phase II: rebuild the northbound frontage road bridge at the lake and demolish the I-35 bridge at Woodland Avenue.
  3. Phase III: rebuild the main lanes at the lake and build the Woodland Avenue pedestrian bridge.
  4. Phase IV: rebuild the southbound frontage road bridge and build the Lady Bird Lake west pedestrian bridge.

So the crossing that is giving the east side of the trail trouble right now is the first new piece of infrastructure the project delivers. The Trail Conservancy expected the east-side closure to last about a year from February 2026. TxDOT also caps continuous full closures of the trail and waterway near the bridge at three per year, each lasting no more than a week. The October 12–18 closure was one of them.

The longer limits are on the water and on Riverside. According to TxDOT, boats passing under the I-35 bridge are limited to a 75-foot-wide passage away from the work zones through 2033. The existing east pedestrian path at the lake and the north sidewalk on Riverside Drive stay closed through 2029.

Woodland Is the Long Wait

Woodland Avenue closed to cars under I-35 in January. KUT reported that the closure ended a crossing that had been in place for decades. The South River City Citizens neighborhood association had argued against it since the proposal surfaced in 2013. KUT also reported that in a 2023 vote, the Austin City Council said the closure "creates a division in the city of more than a mile between the Riverside Drive and Oltorf Street crossings."

That gap is how the detour feels on foot. In the same KUT story, the recommended walking detour from Woodland, uphill to Oltorf Street and back down, was more than a mile.

The permanent fix is a bridge for pedestrians and cyclists, built and paid for by TxDOT. KUT reported that the City Council considered and rejected spending at least $15 million on a 300-foot-wide bridge at Woodland. TxDOT will build a 75-foot-wide one instead, and construction could start as soon as 2029. That puts it in Phase III, two phases after the lake crossing now under construction. In a February update, TxDOT said its crews would build a temporary pedestrian bridge at Woodland in the next phase of the project.

For drivers, Woodland now works as a turnaround rather than a crossing. As of February, TxDOT's posted detours sent eastbound Woodland traffic right onto the southbound frontage road and around through the Oltorf Street U-turn. Westbound traffic went onto the northbound frontage road and through the signal at Riverside Drive. Temporary U-turns in both directions on the frontage road at Woodland are open. In its October roundup of East Austin projects, Community Impact still listed Woodland as permanently closed under I-35. It also reported that several nearby pedestrian paths and road access points stay closed through 2029 or later.

Getting to Riverside on Foot

Riverside is the crossing that stays open for walkers, but it changed in February. Community Impact reported then that TxDOT installed temporary pedestrian signals on Riverside Drive at Manlove Street and Edgecliff Terrace. Pedestrians crossing the river were routed to the existing west sidewalk on the southbound frontage road bridge. TxDOT expected that traffic pattern to stay in place through 2029.

Riverside is also where the lane changes are concentrated. On TxDOT's segment page, the northbound frontage road just north of Riverside is closed to access through 2029. Drivers on Riverside who want northbound use the southbound frontage road, U-turn at Woodland, and take the Riverside Drive bypass lane. The same page says East Avenue under the Lady Bird Lake bridge is closed through late 2026. The finished interchange at Riverside will be a single-point urban interchange.

All of it rolls up into a segment that runs from Holly Street to SH 71/Ben White Boulevard. Construction started in early 2025, Balfour Beatty is the contractor, and TxDOT expects completion in 2033, weather permitting.

The Winter Routine That Doesn't Cross the Highway

None of this touches the middle of the neighborhood. Big Stacy Pool is on its off-season schedule, open from August 31, 2026, into spring 2027 with lap swim and recreational swim hours. It closes on Thanksgiving, Christmas, and New Year's Day. The City of Austin's Big Stacy page has the current hours. Check it before the holidays, since Thanksgiving is two weeks after this post goes up.

A walk that starts at Big Stacy and heads toward the lake runs into construction only at the I-35 end. For the next few months, the South Congress bridge and the west-side I-35 sidewalk are the shortest ways across the water. The east-side crossing is on track to return as a new bridge in the first phase. Woodland is the crossing on the multiyear timeline. For more about the streets between SoCo and the highway, our day in Travis Heights covers the side of the neighborhood that stays the same.

If you're weighing how the I-35 work changes daily life on your block in Travis Heights, or what it means for timing a sale or purchase near the highway, Levack Living can walk through it with you. Schedule a personal market consultation, and we'll go street by street through what the construction phases mean for your plans.